How to apply for electricity (Kenya Power) connection
There are 3 Easy Steps of applying for an electricity (Kenya Power) connection as follows:
Procedure 1: Submit application for supply of electricity to Kenya Power and Lighting Company (KPLC) sign the supply contract form below. (8 days)
Procedure 2: Pay estimate. (1 day)
To fill the form online visit https://selfservice.kplc.co.ke and select New Supply Application.
Procedure 3: Receive external works, meter installation and electricity flow. (75 days)
NB: You will need to submit copies of your ID/PIN as may be applicable.
Please make sure you have the following:-
A soft copy of National Identification (I.D) or Passport for Non-Kenyans (PDF, MS Word).
A soft copy of route sketch leading to premises where supply is required.
Copy of the PIN Certificate
Wiring certificates
Supply contract form
Consent from the owner of the property
http://www.kplc.co.ke/img/full/GOSS9XbKP72N_ENQUIRY%20FOR%20SUPPLY%20OF%20ELECTRICITY.pdf
Requirements for Corporates
A soft copy of Certificate of Registration.
A soft copy of route sketch leading to premises where supply is required.
Copy of the PIN Certificate
A Scaled site plan for Industries, Housing Estates, shopping malls etc.
Consent from the owner of the property
Supply contract form (signed)
Wiring Certificates (signed
I want power at Ekalakala sub location.
supply in our home compound of five houses each with own meter,we are located between kithunguini market and kikawani primary .machakos county
Lucky from kilifi county magarini sub-County marafa center i need a sub prepaid meter
I need electricity power connection in my house at wamunyu town,machakos County
I want power at my home in kisiiki,matuu subcounty